# Power Play: PJM's Data Center Plan on Hold

Newsy: Data Centre & Infrastructure Digest
Published: 2026-10-01T01:17:00.611Z
Source: https://newsyai.com/edition/e9c00923-2e45-434e-838d-8bf8eeba3238
Archive: https://newsyai.com/newsy/24c3f9f5-7850-4915-9942-f6be492ab1c1.md

---

**# Intelligence Briefing: Bare-Metal Data Center Market – October 1, 2026**

**Top 3**

**PJM Interconnection’s 6.8 GW data-center power procurement plan accepted but suspended until February 28, 2027, for revisions on cost allocation, collateral, and exit rules.**  
On September 30, 2026, FERC approved key elements of the plan to address AI-driven demand shortfalls in its territory but paused implementation for a paper hearing, citing consumer protection concerns. Primary source: [energyconnects.com](https://www.energyconnects.com/news/utilities/2026/september/biggest-us-grid-s-data-center-plan-accepted-with-5-month-pause/); [reuters.com](https://www.reuters.com/business/energy/ferc-asks-grid-operator-pjm-revise-plan-shield-homes-data-center-costs-2026-09-30/).  
*Matters because extended timelines and higher scrutiny in the largest U.S. grid region reinforce grid constraints that slow hyperscaler builds, creating openings for established regional bare-metal providers with existing Midwest utility ties.*

**Dubuque, Iowa, City Council approves a six-month moratorium on hyperscale data centers effective immediately.**  
On September 22, 2026, the council enacted the pause on facilities exceeding thresholds such as 100,000 sq ft, 75 MW demand, or high water use while drafting permanent rules on utilities and annexation. Primary source: [kcrg.com](https://www.kcrg.com/2026/09/22/dubuque-city-council-passes-temporary-moratorium-hyperscale-data-centers/).  
*Matters because additional local regulatory friction in eastern Iowa further delays large projects and favors smaller, community-aligned regional operators.*

**Bare Metal Server Price Index holds steady at a $155.10 median monthly plan as of September 30, 2026.**  
The index reflects a modest 3.2% rise over 143 days with no sharp movements across tracked providers. Primary source: [baremetalindex.com](https://www.baremetalindex.com/data/).  
*Matters because pricing stability allows regional bare-metal operators to compete on reliability, locality, and service rather than aggressive discounting against larger resellers.*

## Data Center Industry — New Builds, Expansions, Closures, and M&A in the US; Iowa or Midwest Focus; Capacity and Vacancy Trends; Hyperscaler Expansion Plans

**Iowa Data Center Investment Tracker reports $7.0B in commitments amid multiple blocked, delayed, or restricted projects as of September 30, 2026.**  
The tracker lists three named sites (primarily Google-related) against 16 blocked/delayed/restricted projects and ongoing moratoria in several jurisdictions. Primary source: [savrn.com](https://savrn.com/data-center-capital-atlas/iowa).  
*Matters because persistent local resistance and regulatory pauses in Iowa tilt the environment toward nimble regional providers over delayed hyperscale timelines.*

**Nothing significant** on new U.S. builds, expansions, closures, M&A, specific hyperscaler plans in the Midwest, or capacity/vacancy trends beyond the regulatory and pipeline context already noted.

## Bare Metal and Dedicated Hosting Market — Pricing Changes, Renewal Increases, Outages, Acquisitions, or Product Moves

**Bare Metal Server Price Index remains stable (detailed in Top 3).**  
No sharp shifts or new provider-specific moves reported. Primary source: [baremetalindex.com](https://www.baremetalindex.com/data/).  
*Matters because steady pricing supports differentiation through service and location for small regional operators.*

**Nothing significant** on pricing changes, renewal increases, outages, acquisitions, product moves, or customer-migration chatter from Latitude.sh, Hetzner, Hivelocity, Cherry Servers, OVHcloud, Equinix, Vultr, or new entrants.

## Narrative Opportunities — Public or Political Backlash, Cloud Price-Hike Coverage, Cloud-Repatriation Stories, Data Sovereignty Debates, “Big Tech vs. Local Community” Coverage

**Dubuque moratorium and continued Iowa local opposition underscore “big tech vs. local community” tensions.**  
Recent actions in Dubuque and other Iowa jurisdictions highlight community concerns over scale, utilities, and land use. Primary sources: [kcrg.com](https://www.kcrg.com/2026/09/22/dubuque-city-council-passes-temporary-moratorium-hyperscale-data-centers/); [savrn.com](https://savrn.com/data-center-capital-atlas/iowa).  
*Matters because public framing of hyperscale projects as external pressures strengthens preference for independent regional infrastructure providers.*

**Nothing significant** on cloud price-hike coverage, repatriation stories, or data sovereignty debates.

## Power and Energy — Grid Capacity Constraints, Power Pricing, Wind and Solar Generation in Iowa and the Midwest, Utility Deals with Data Centers, Energy-Related Permitting Fights

**PJM plan suspension and FERC large-load tariff reforms (detailed in Top 3 and Regulation section).**  
No new Iowa-specific wind/solar generation or utility deal updates reported.

## GPU and AI Compute Market — Reserved vs. Spot Pricing Shifts, GPU Supply and Availability, Neocloud News, Teams Moving AI Workloads to Dedicated Hardware

**Nothing significant** on reserved-vs-spot pricing shifts, GPU supply/availability, neocloud announcements, or AI workload migrations to dedicated hardware.

## Blockchain Infrastructure (Brief) — Solana Validator Ecosystem News, Solana Foundation Delegation Program Changes, Validator Hosting and Hardware News, Monad Mainnet Progress

**Solana Alpenglow testnet performance at 54 ms median finality (ongoing from prior reporting).**  
No new updates on Solana Foundation Delegation Program, validator hosting/hardware shifts, or Monad mainnet progress. Primary source: [cryptobriefing.com](https://cryptobriefing.com/solana-alpenglow-54ms-finalization-testnet/).  
*Matters because faster finality on testnet may increase demand for low-latency dedicated hardware suitable for validators.*

## Regulation and Incentives — State Tax Incentives for Data Centers (Iowa Especially), Federal or State Regulation of Data Center Energy Use

**FERC show-cause orders on large-load interconnection tariffs across all six U.S. RTOs/ISOs (September 25, 2026) and Dubuque moratorium (detailed above).**  
FERC directed grid operators to justify or reform rules within 60 days on application processes, cost allocation, co-location, and flexible services. Primary source: [ferc.gov](https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration).  
*Matters because nationwide tariff reforms could extend timelines and raise costs for new large loads, benefiting established regional providers.*

**Nothing significant** on new state tax incentives.

**Sources tracked via primary reporting and official trackers as of October 1, 2026. No material updates repeated from prior editions.**